Understanding The Data Center Map
A short guide to what the map actually shows, the terms you'll see on it, and why "who pays" is the real story behind every dot.
Why we built this
AI's growth runs on electricity, and that electricity has to come from somewhere. Every dot on the map is a real, filed request to connect a data center to the regional power grid — not a projection, not a rumor. Here's the scale we're currently tracking.
Key terms on the map
You don't need an engineering background to read this. Here's what each field actually means.
The literal waiting line a data center joins to connect to the regional power grid. Getting approved locally (by a county) is separate from getting a grid connection — a project can be zoned and built but still waiting years in this queue.
Megawatts requested — a rough proxy for size. For context, 1,000 MW (1 GW) is roughly enough continuous power for 750,000 average homes. This map now spans five genuinely separate power grids: PJM (VA, MD, NC, SC, PA, and most of OH, where AEP Ohio sits inside PJM territory), ERCOT (Texas, independent), Southern Company/SERC (Georgia), WECC (Arizona, the Western grid), and MISO (Louisiana, served by Entergy). Worth remembering when comparing grid-strain numbers across states.
The specific utility (like Dominion Energy or SMECO) or the regional grid operator (like PJM or ERCOT) responsible for actually delivering the power. This is the single biggest factor in how a project's costs get split.
Where the project actually stands right now — see the table below. This is the field that changes most often and is worth rechecking.
| Status | What it means |
|---|---|
| PROPOSED | Filed with a county or utility, but not yet approved. Most vulnerable to community opposition or denial at this stage. |
| APPROVED | Cleared local zoning or regulatory review, but construction hasn't visibly started yet. |
| CONSTRUCTION | Approved and actively being built. |
| OPERATIONAL | Built and running. |
| DENIED / PAUSED | Formally rejected, voided by a court, or voluntarily withdrawn by the developer. |
| UNKNOWN | Status genuinely isn't public yet — this means "not disclosed," not "we didn't check." |
Funding Source: the real story
This is the field that matters most, because it answers the question everyone actually wants to know: when a data center needs new power lines or a substation, who's paying for that buildout — the company, or everyone else on the grid?
Dominion's new GS-5 large-load rate class (2025–2027) is designed to shift more infrastructure cost onto data centers specifically, but full cost allocation is still being litigated by the Virginia State Corporation Commission as of mid-2026. Neither fully ratepayer-funded nor fully developer-funded yet — it's in between, and still moving.[1]
Southern Maryland Electric Cooperative has stated outright: any data center connecting in its territory must directly pay 100% of the transmission and distribution buildout and ongoing costs required to serve it.[2]
Maryland's Office of People's Counsel filed a FERC complaint estimating residential ratepayers will pay an extra $1.6 billion over the next decade specifically because of how PJM (the regional grid operator) allocates the cost of grid upgrades — cost the complaint says falls "mostly" on BGE and Pepco customers, which implies some smaller exposure elsewhere in Maryland's PJM footprint too, not zero.[3]
North Carolina has no statewide data center law at all — which is exactly why more than a dozen counties have written their own rules from scratch. In Person County, officials signed NDAs and withheld Microsoft's identity from the public for roughly 16 months while negotiating a 1,385-acre megasite, and denied records requests without citing the legal exemption state law requires. The funding structure wasn't the mystery — who the county was even funding was.[4]
Two South Carolina Senate bills that would have set placement restrictions both failed this year. With no statewide standard, nine counties have passed their own moratoriums — and two major projects (TigerDC's $3B Spartanburg campus, Stream Data Centers' Marion County site) were withdrawn entirely after local pushback, before a funding structure was ever finalized.[5]
Smaller rural electric co-ops serving several Texas sites have no public large-load tariff on file. Some of the largest projects sidestep the question entirely — Amazon's Pecos County site is building its own off-grid natural gas plant rather than drawing from the public grid at all.[6]
Georgia's Public Service Commission approved 9,985 MW of new generation in December 2025 — about 80% expected for data centers. Georgia Power agreed to personally "backstop" the cost through 2031 if demand doesn't materialize, and any data center over 100MW must fund its own grid buildout. But a sitting PSC Commissioner is currently investigating a "Real Time Pricing" loophole his office says lets large customers avoid nearly $1 billion in costs everyday ratepayers still cover.[7]
Unlike every other state here, Arizona's legislature can't set utility rates at all — that authority belongs exclusively to the elected Arizona Corporation Commission (ACC). In 2026 lawmakers passed a 3-year pause on the state's data center tax incentive, but a bill that would have forced data centers over 100MW to cover their own power costs died without a hearing. Meanwhile APS and Tucson Electric Power are both seeking 14% rate increases for 2026, citing data center demand, using a new annual rate-adjustment formula the ACC approved in 2025 over its own staff's warnings. Attorney General Kris Mayes has intervened, arguing the formula shifts financial risk onto ratepayers. The ACC also approved "Project Baccara," a data center that starts on self-generated gas power before later connecting to the public grid — critics say the arrangement could still leave ratepayers exposed once that backup gas capacity becomes a permanent draw.[8]
Ohio's biggest project by far is being built on the former Portsmouth Gaseous Diffusion Plant — a Cold War-era federal uranium enrichment site in Pike County. OpenAI signed a 20-year lease for ~8 gigawatts of capacity; NVIDIA is investing $1.5 billion directly into developer SB Energy. The notable part for ratepayers: SB Energy has stated publicly it will fund 100% of the cost of grid upgrades and new transmission infrastructure itself — the same clean, developer-pays model as Maryland's SMECO, just at a vastly larger scale ($30-40 billion for the first phase alone).[9]
Meta's Hyperion campus in rural Richland Parish is one of the largest AI data centers ever planned. In October 2026, Entergy Louisiana disclosed for the first time that it will draw about 4,500 MW — roughly four times what the entire city of New Orleans uses. Regulators approved Entergy's first three gas plants for the site in 2025; Entergy is now asking the Louisiana Public Service Commission to approve a $12.9 billion buildout of more generation, battery storage and transmission, with a final vote scheduled for December 16, 2026. Entergy says Meta pays its full cost of service and promises $2.65 billion in customer savings over 20 years. Opponents question whether everyday ratepayers will still carry risk if demand shifts, and the commission declined to investigate Meta's outside financing deal with Blue Owl Capital.[10]
In 2025, Governor Josh Shapiro celebrated Amazon's $20 billion data center commitment as the largest private investment in state history. By August 2026, with more than 100 proposals in play, he signed Executive Order 2026-05. It pulls data center projects out of the state's Fast Track permitting program, bars state agencies from signing nondisclosure agreements on them, and directs regulators to keep data centers solely responsible for the grid upgrades needed to serve them. Developers must make a legally binding commitment to the state's GRID requirements before environmental permits are reviewed. Critics on both sides say it goes too far or not far enough, and projects already moving, like Aligned's 2 GW Project Phoenix and the 4.5 GW gas plant at Homer City, are building their own on-site power rather than waiting on the grid.[16]
How to actually use the map
Filter by Status to see what's actually built versus what's still just a proposal. Filter by Utility/ISO to compare how different power providers are handling the same growth. Filter by State to compare how ten very different regulatory environments are handling identical pressure. Click any dot for the full project record, including its funding source and our source link — every data point traces back to a filing, a news report, or a utility document, never a guess.
Glossary
-
PJM
The regional grid operator coordinating electricity across 13 states plus DC, including Virginia, Maryland, North Carolina, South Carolina, Pennsylvania, and most of Ohio. When PJM's costs go up, they get divided among every utility in its footprint — which is how Maryland ends up paying for grid upgrades driven partly by growth elsewhere in the region.
-
ERCOT
Texas's own independent grid operator, separate from PJM. Texas data centers are subject to entirely different capacity and reliability rules than everything else on this map — a genuinely different system, not just a different utility.
-
WECC
The Western Electricity Coordinating Council — a third distinct grid system covering Arizona and the broader Western US. Arizona's utility rates are set exclusively by its Corporation Commission, not its legislature, a structural quirk unique among the states on this map.
-
MISO
The Midcontinent Independent System Operator — the grid operator covering Louisiana and much of the central US, from the Gulf Coast to Canada. Louisiana's rates are set by its elected Public Service Commission, and Entergy is the utility building the power supply for Meta's Hyperion campus.
-
Large-load tariff
A special utility rate category built specifically for very large power users like data centers, separate from normal residential or commercial rates. Several states are actively writing these right now — which is exactly why "Funding Source" keeps changing.
-
By-right development
Construction a developer can pursue without needing special county approval, because the site is already zoned for it. Several Virginia counties have recently eliminated by-right data center development, requiring a special exception instead — while some North Carolina localities (like Petersburg) still allow it, which is part of why approvals move faster there.
-
Grandfathering
When new, stricter rules exempt projects that were already filed before the rule changed. Whether a county grandfathers old applications is often what decides which projects survive a policy shift.
-
Behind-the-meter / off-grid
A facility that generates its own power on-site rather than drawing from the public grid — Amazon's Pecos County, Texas site is one example, with its own natural gas plant permitted for up to 33 million tons of CO2/year. Ohio's PORTS-Pike campus takes a hybrid approach: built on federal land with its own dedicated new generation, but still connected to AEP Ohio's grid.
Sources
- Virginia Mercury, "SCC orders Dominion to develop tariff to assign more transmission costs to data centers," Aug 2026.
- Calvert County Government, SMECO data center policy presentation, 2026.
- Maryland Office of People's Counsel, FERC complaint re: PJM regional transmission cost allocation, filed May 2026.
- The Assembly NC, "Person County, Microsoft data center nondisclosure agreements," 2026.
- SC Daily Gazette, "Data center proposals on the decline according to SC utility companies," Mar 2026; DataCenterDynamics, TigerDC withdrawal coverage, Feb 2026.
- DataCenterDynamics, "Amazon acquires 8,000-acre site in Pecos, Texas for natural gas-powered behind-the-meter data center," 2026.
- Georgia Public Service Commission, "Data Center Fact Sheet," March 2026; GovTech, "Georgia Regulators Investigating Who Pays Data Center Costs," 2026.
- Arizona Corporation Commission, "ACC Data Center/Large Load Workshop Highlights," April 2026; AZ Capitol Times, "Who pays for Arizona's AI power boom?" and "Data centers dominated 2026 session," 2026; AZCE, "Arizona Utilities Push 14% Rate Hikes as Data Centers Drive Soaring Energy Demand," Oct 2025.
- OpenAI, "OpenAI joins PORTS-Pike project," Aug 2026; DataCenterDynamics, "Nvidia confirms it will back 4.25GW of OpenAI capacity at Ports-Pike mega data center," 2026; ConstructConnect, "NVIDIA, OpenAI Back 'World's Largest AI Data Center' at Ohio's PORTS-Pike Site," 2026.
- Louisiana AI, "4,500 megawatts: Entergy's Meta power hearing puts Louisiana's AI buildout on trial," Oct 2026; Data Center Census, Meta Hyperion LPSC docket timeline (U-37882), 2026; Black Ridge Research, "Meta Hyperion AI Data Center Project Updates," 2026.
- DataCenterDynamics, ongoing Virginia, Maryland, North Carolina, South Carolina, Texas, Georgia, Arizona, Ohio, Louisiana, and Pennsylvania project coverage, 2024–2026.
- ComputeLaw Blog, "Virginia siting rules and local moratoriums for AI data centers," 2026.
- WJLA / 7News, Prince William County Board of Supervisors coverage, 2026.
- Frederick County Government and Frederick News-Post, data center zoning coverage, 2025–2026.
- JLARC (Joint Legislative Audit and Review Commission), Virginia data center electricity demand report, 2026.
- Office of the Governor of Pennsylvania, "Governor Shapiro Signs Executive Order on Data Center Development" (EO 2026-05), Aug 18, 2026; Morgan Lewis, "Governor Shapiro Issues Executive Order Imposing New Requirements for Data Centers," Aug 2026; Pennsylvania Capital-Star, Shapiro executive order coverage, Aug 2026.